City of Toronto Downtown Construction Update #11

Downtown Construction Update (Shuter Street)


Watermain Replacement, Road Resurfacing and Trench Restoration
on Shuter Street From Yonge Street to Sherbourne Street


Contract #: 16ECS-TI-18SP

Expected Start Date:  August 8, 2016

Expected End Date:  October 28, 2016

New End Date: December 30, 2016

The City of Toronto's work replacing the 140-year-old watermain and the City-owned portion of 
substandard water services on Shuter Street from Yonge Street to Sherbourne Street continues.
This Construction Update provides you with new information about work delivery and the project status.

Please be advised that better than anticipated progress was made last week with respect to the watermain installation work at the intersection of Shuter St. and Bond St. As a result of this, the Contractor has requested to extend their work area from Victoria Street to Bond Street. 
This work will begin on Tuesday November 15th at 7:00 am.

The estimated duration of this work is 5 days. During the work, one way traffic will be maintained
westbound, and two way traffic will be provided at the end of each day.

Map Of Work Area

 

Work Details 

· Complete Milling

· Concrete base repairs

· Placing asphalt base

· Top asphalt will be installed at a later date, from Victoria to Church, once all watermain work has been completed.

· An additional update will be provided before this work begins.
 

Work Hours: This project will use periods of extended hours and overnight work. The contractor will complete most work Monday to Saturday, 7:00 a.m. to 7:00 p.m., with work after hours/overnight and on Sundays as required.

Extended work hours help to minimize traffic disruption, congestion and to shorten the project duration.

Traffic Management: Efforts have been made to manage traffic in the area for the safety of workers, road users and residents.

Road users should expect delays and increased traffic on nearby main and side streets.

· During the work, one way traffic will be maintained westbound, and two way traffic will be provided at the end of each day

Water Service Disruptions: From time-to-time, the water supply to your property will be shut-off to complete construction; the contractor will provide at least 24-hour advance notice. Throughout the work, it is recommended that you temporarily disconnect any water treatment systems (i.e. softeners or filters), water-cooled air conditioners or similar plumbing fixtures. Automatic lawn sprinkler systems may also be affected, therefore, you may need to water manually. In the event you did not received advanced notice, an emergency water shut off could have been necessary.

Road and Sidewalk Access: In order to complete the work in a safe manner, there will be road and sidewalk restrictions within the construction work zone. Access for emergency vehicles will be maintained at all times.

Driveway Access: The contractor will notify you of any temporary restrictions to your driveway access. If your property has two entrances, one entrance will be kept open at all times.

Parking: Parking in the active work zone is not permitted due to space requirements for construction equipment and materials. If your parked vehicle affects the construction work, it will be re-located with no charge to the owner. If

your vehicle is moved, please contact parking control for its location at416-808-2222.

Cyclists: If travelling on Shuter Street, please share the traffic lane in the active work zones.

Garbage & Recycling: Please follow your normal routine. If required, the contractor will move bins to an appropriate location and return them.  Please ensure that you label your bins with your address.